Estimated Timeline
November 17, 2015 – Official ground-breaking ceremony
January 2016 – Site servicing and excavating taking place. Construction crane erected
Spring 2016 – Work begins on ground floor
Summer 2016 – Basic structure of expansion takes shape
November 2016 – Building will be weather tight. Construction crane taken down
November 7, 2017 – Expansion opens, finishing touches continue
The Great Expansion
- Total cost: $98.3 million
- 106,000 sq. ft.
- Three storeys plus basement
- Future home of STEGH’s emergency department, medical device reprocessing facility, surgical suites and mental health and addiction services unit